22 Sep Work on Design and Build of Th. Guraidhoo Harbour is underway
Work on Design and Build of Th. Guraidhoo Harbour is underway, with overall 4% project progress. Harbour Basin Dredging works for the project is currently ongoing, with 33% completion.
Project works consists of; dredging and excavation operations of 16,533cbm; construction of a 208m breakwater; a 22m revetment; a 370m quay wall and 370sqm of paved area. The estimated value of the project is MVR 46.01 million. The project was awarded on 01st October 2019.