Work on Design and Build of Sh. Foakaidhoo Harbour is underway, with overall 41% project progress. The second shipment of rock boulders required for the breakwater construction have been delivered to the project site.
The Sh. Foakiadhoo Harbour project consists of; new harbor basin dredging operations of 39,995cbm; existing harbor basin dredging operations of 1800cbm; channel dredging operations of 4000cbm; construction of a 507m breakwater; a 100m revetment; a 464m quay wall; 2,320 sqm of paved area and installation of navigation lights and streetlights. The value of the project is MVR 52.7 million.