05 Nov Work on Design and Build of Sh. Feevah Harbor is well underway
Work on Design and Build of Sh. Feevah Harbor is well underway, with overall 61% project progress. Construction of breakwater and installation of precast concrete blocks required for quay wall construction are currently ongoing, with 53% and 41% completion respectively.
Scope of works for the project include dredging and excavation operations of 55,163cbm; the construction of a 464m quay wall; a 356m breakwater; 182m revetment, and installation of 2,320sqm of paved area. The value of the project is MVR 69.3 million. The project was awarded on 02 July 2019.
Sorry, the comment form is closed at this time.