Work on Design and Build of Sh. Feevah Harbor is well underway

Work on Design and Build of Sh. Feevah Harbor is well underway, with overall 61% project progress. Construction of breakwater and installation of precast concrete blocks required for quay wall construction are currently ongoing, with 53% and 41% completion respectively.
Scope of works for the project include dredging and excavation operations of 55,163cbm; the construction of a 464m quay wall; a 356m breakwater; 182m revetment, and installation of 2,320sqm of paved area. The value of the project is MVR 69.3 million. The project was awarded on 02 July 2019.