Work on Design and Build of Sh. Feevah Harbor is underway.

Work on Design and Build of Sh. Feevah Harbor is underway. Concrete works required for the construction of quay wall is currently ongoing.
Scope of works for the project include dredging and excavation operations of 31,303cbm; the construction of a 464m quay wall; a 504m breakwater; 70m revetment, and installation of 2,320sqm of paved area. The estimated value of the project is MVR 69.3 million. The project was awarded on 02 July 2019.