Work on Design and Build of S. Meedhoo Harbour is well underway, with overall 80% project progress. Channel Dredging works and quay wall works for the project is currently ongoing, with 34% and 85% completion respectively.
Scope of works for the project include dredging 35,496cbm from harbor basin, dredging 22,500cbm from channel; the construction of a 496m quay wall; and a 115m rock boulder breakwater. Additionally, the installation of harbor lights, installation of 2,480 sqm of paved area will also be undertaken. The value of the project is MVR 33.4 million. The project was mobilized on 18th September 2019.