10 Nov Work on design and build of S. Hulhudhoo Harbour is underway
Work on design and build of S. Hulhudhoo Harbour is underway, with overall 38% project progress. Dredging works for the project is currently ongoing, with 53% completion.
The S. Hulhudhoo Harbour project consists of; dredging and excavation operations of 88,623cbm; construction of a 114m breakwater; a 624m revetment; a 742m quay wall; 2,250 sqm of paved area and installation of streetlights. The value of the project is MVR 65.1 million. The project was awarded on 01 March 2020.
Sorry, the comment form is closed at this time.