10 Apr Work on design and build of S. Hulhudhoo Harbor Development Project is well underway
Posted at 11:10h
in
News
by Samahath Zuhuree
Work on design and build of S. Hulhudhoo Harbor Development Project is well underway, with overall 83% project progress. We have completed construction of quay wall. Harbor bridge works are currently ongoing.
The S. Hulhudhoo Harbour project consists of; dredging and excavation operations of 88,623cbm; construction of a 114m breakwater; a 624m revetment; a 742m quay wall; 2,250 sqm of paved area and installation of streetlights. The value of the project is MVR 66.3 million.