Work on design and build of S. Hulhudhoo Harbor Development Project is well underway

Work on design and build of S. Hulhudhoo Harbor Development Project is well underway, with overall 93% project progress. Second shipment of rock boulders required for the project have been delivered to the site.
The S. Hulhudhoo Harbour project consists of; dredging and excavation operations of 88,623cbm; construction of a 114m breakwater; a 624m revetment; a 742m quay wall; 2,250 sqm of paved area and installation of streetlights. The value of the project is MVR 66.3 million.
No Comments

Sorry, the comment form is closed at this time.