28 Dec Work on Design and Build of R. Rasmaadhoo Harbour is underway
Work on Design and Build of R. Rasmaadhoo Harbour is underway, with overall 11% project progress. Rock boulders needed for the project have been unloaded to the project site on 28 December 2020.
Project works consists of; new harbor dredging operations of 7,500cbm; existing harbor basin dredging operations of 1,000cbm; entrance channel dredging operations of 500cbm; construction of a 377m breakwater and installation of 600sqm of paved area. The estimated value of the project is MVR 18.7 million. The project was mobilized on 26th July 2020.