21 Sep Work on design and build of R. Kinolhas Harbor Development Project is well underway
Work on design and build of R. Kinolhas Harbor Development Project is well underway, with overall 60% project progress. We have completed channel dredging operations.
Scope of works include, dredging and excavation operations, construction of a 162m groyne, a 285m breakwater, a 65m revetment, a 186m quay wall, a ramp, installation of a 1663.36sqm harbor pavement, navigational aids and harbor lights. The value of the project is MVR 45.1 million.