Work on Design and Build of N. Landhoo Harbour is well underway

Work on Design and Build of N. Landhoo Harbour is well underway, with overall 26% project progress. Dredging works for the project is currently ongoing, with 65% completion.
Scope of works for the project include dredging and excavation operations of 25,000cbm; the construction of a 256m quay wall; a 401m breakwater; and a 60m revetment. Additionally, the installation of navigation lights, streetlight and installation of 1,280sqm of paved area will also be undertaken. The estimated value of the project is MVR 35.60 million. The project was awarded on 10th December 2019.