21 Dec Work on Design and Build of L. Isdhoo Harbour is underway
Work on Design and Build of L. Isdhoo Harbour is underway. Major dredging works for the project has been completed. We are now preparing to commence installation of precast concrete blocks required for quay wall construction.
Scope of works for the project include dredging and excavation operations of 27,129cbm; the construction of a 230m quay wall; a 208m breakwater; and a 98m revetment. Additionally, the installation of 1,560sqm of paved area and installation of harbor lights will also be undertaken. The value of the project is MVR 34.7 million. The project was mobilized on 04th August 2020.