Work on Design and Build of F. Dharanboodhoo Harbour is well underway

Work on Design and Build of F. Dharanboodhoo Harbour is well underway, with overall 32% project progress. Installation of precast concrete blocks required for quay wall construction has commenced on 10th December 2020.
The F. Dharanboodhoo harbor development scheme consists of dredging and excavation operations of 46,600cbm, breakwater construction of 399m, quay wall construction of 253m, revetment construction of 150m, installation of 2,500 sqm paved area and installation of harbor lights.