07 Dec Work on design and build of F. Dharanboodhoo Harbor is well underway
Work on design and build of F. Dharanboodhoo Harbor is well underway with overall 88% project progress. We have completed construction of harbor bridge. Construction of breakwater is currently ongoing, with 83% project progress.
Scope of works for the project include dredging and excavation operations of 46,600cbm; the construction of a 253m quay wall; a 410m breakwater; a 64m revetment; installation of 2,500sqm of paved area and installation of harbor lights. The value of the project is MVR 40.2 million.