01 Jul Work is well underway for design and build of S. Meedhoo harbour upgrade; with 60% overall project progress
Work is well underway for design and build of S. Meedhoo harbour upgrade; with 60% overall project progress.The scheme for this project involves existing harbour basin’s dredging operations of 35,496cbm; channel entrance dredging of 22,500cbm; the construction of a 115m rock boulder breakwater; a 496m quay wall and 2,480qm paved area.