Work is well underway for design and build of S. Meedhoo harbour upgrade; with 60% overall project progress

Work is well underway for design and build of S. Meedhoo harbour upgrade; with 60% overall project progress.The scheme for this project involves existing harbour basin’s dredging operations of 35,496cbm; channel entrance dredging of 22,500cbm; the construction of a 115m rock boulder breakwater; a 496m quay wall and 2,480qm paved area.
Overall scope of works for the project is valued at MVR 35.4 million. The project, which was awarded to us on 23rd June 2019, was subsequently mobilized on 18th September 2019.