Work is well underway for design and build of R. Madduvari South Harbor

Work is well underway for design and build of R. Madduvari South Harbor; with 90% of harbor basin dredging and 95% of channel dredging complete.
The scheme for this project involves dredging operations of 72,800cbm; along with construction of a 411m breakwater; a 135m revetment; a 566m quay wall and 2,825sqm paved area. The scheme also includes navigation and streetlights installation.
Overall scope of works for the MVR 68.66 million project is targeted to be completed within 590 days. The project, which was awarded to us on 26th August 2019, was subsequently mobilized on 29th November 2019.
No Comments

Sorry, the comment form is closed at this time.