Work is well underway for design and build of HA. Kelaa Harbour Phase Two

Work is well underway for design and build of HA. Kelaa Harbour Phase Two; with completion of channel dredging works, maintenance dredging and installation of mooring buoys. Work on revetment construction is currently ongoing.
The scheme for this project involves maintenance dredging operations of 3,496cbm; channel dredging of 12, 768cbm; along with construction of a 30m breakwater; a 220m revetment; a 50m quay wall and 1,445sqm paved area. The scheme also includes mooring buoys and streetlights installation.

Overall scope of works for the MVR 17.4 million project is targeted to be completed within 410 days. The project, which was awarded to us on 30th June 2019, was subsequently mobilized on 13th September 2019.

No Comments

Sorry, the comment form is closed at this time.