We have mobilized our project team to Dh. Hulhudheli harbor project site

We have mobilized our project team to Dh. Hulhudheli harbor project site on 25th June 2020. The project which received EIA approval on 30th April 2020 involves the design and build of Dh. Hulhudheli harbour upgrade.
Among others, project works involve dredging and excavation of 45,585cbm; the construction of a 277m long breakwater; a 432m quay wall, 60m groynes and a 60m revetment. The project also includes the construction of 2160sqm of paved area as well as the installation of streetlights and mooring blocks.
Overall, the project which was awarded on 10th December 2019, is estimated to cost MVR 39.8 million. The project is estimated to be completed within 362 days.
No Comments

Sorry, the comment form is closed at this time.