03 Jul We have mobilized Hdh. Finey Harbor Development Project site
We have mobilized Hdh. Finey Harbor Development Project site on 3rd July 2024.
Scope of works include, 5,848.05cbm maintenance dredging operations, 35,484.26cbm new harbor basin dredging operations, 5,848.05cbm channel dredging operations, construction of a 219m breakwater; a 82m revetment; a 25m groyne; a 248m quay wall; installation of 2,198.65sqm harbor pavement, construction of a ramp (10m x 9m), installation of harbor lights and mooring buoys. The value of the project is MVR 44.59 million.