04 May We have completed the construction of GA. Vilingili harbour Phase Two
We have completed the construction of GA. Vilingili harbour Phase Two. The project, which was awarded to us in August 2019, was completed in April 2020.
Project work includes the construction of a 346 m breakwater; the construction of a 30 m bridge: and the installation of harbour beacons. The project is valued at MVR. 10.6 million.