We have commenced installation of precast concrete blocks for the quay wall construction of K. Himmafushi Harbor Development Project (phase 2).

We have commenced installation of precast concrete blocks for the quay wall construction of K. Himmafushi Harbor Development Project (phase 2).
Scope of works include, dredging and excavation operations of 14,300cbm for new harbor basin, construction of a 38m breakwater, a 248m revetment, 172m quay wall and installation of navigational aids. The value of the project is MVR 25.88 million.