We have commenced construction of bund wall in preparation for reclamation operations of R. Alifushi Land Reclamation and Airport Development Project.

We have commenced construction of bund wall in preparation for reclamation operations of R. Alifushi Land Reclamation and Airport Development Project.
Scope of works involve, reclamation operations of 50.5 hectares, construction of a 2871m revetment, a 480m groyne, construction of runway, apron, taxiway, and service roads, terminal building, fire building, installation of firefighting equipment and a 655m security fence. The value of the project is MVR 451.6 million.
No Comments

Sorry, the comment form is closed at this time.