23 Jun The third shipment of rock boulders required for the Ha. Dhidhoo Harbor Extension & Jetty project has been delivered to the site
The third shipment of rock boulders required for the Ha. Dhidhoo Harbor Extension & Jetty project has been delivered to the site. Furthermore, the variation works of quay wall blocks installation and new harbor basin dredging are complete. Additionally, the progress of the existing harbor basin dredging work is at 87% completion.
Project works involve, dredging and excavation operations of 78,000cbm; construction of a 49m breakwater; a 58m groynes, a 81m channel breakwater, a 768m revetment; a 898m quay wall; installation of 9,270sqm harbor pavement and installation of harbor lights. The value of the project is MVR 88.36 million.
Sorry, the comment form is closed at this time.