The third shipment of rock boulders for N. Velidhoo Boat Beaching Area Project has been delivered to project site

The third shipment of rock boulders required for the N. Velidhoo Boat Beaching Area Project has been delivered to the project site, and breakwater bed preparation works have been completed. Furthermore, breakwater profiling work is scheduled to begin next.
Scope of works include, reclamation operations of 1.5 hectares, levelling 138,247sqm of the reclaimed area, construction of a 214m revetment and 100m breakwater. The value of the project is MVR 19.4 million.