The seventh shipment of rock boulders required for the Sh. Milandhoo Shore Protection project has been delivered to the site

The seventh shipment of rock boulders required for the Sh. Milandhoo Shore Protection project has been delivered to the site. Furthermore, the revetment profiling work and groyne installation work are in progress, with 55% and 65% completion, respectively. The overall project completion is currently at 58%
Scope of works involve, construction of a 954m revetment and construction of a 115m groyne. The value of the project is MVR 34.6 million.