The mobilization of Harbour Repair and Dredging in R. Vandhoo project was undertaken on 20th June 2020

The mobilization of Harbour Repair and Dredging in R. Vandhoo project was undertaken on 20th June 2020.
Among others, project works include but is not limited to the demolition of existing cement bag wall structures and depositing the debris; dredging and excavation works of the harbor basin of 1,870 cbm; and the construction of a 75m quay wall. The delivery and installation of precast blocks and backfilling of quay walls with dredged materials will also be undertaken. Overall, the project which was awarded on 26th August 2019, is valued at MVR 5.99 million.