02 Sep The jetting machine needed for S. Maradhoo-Feydhoo Sewerage project was cleared and tested yesterday
The jetting machine needed for S. Maradhoo-Feydhoo Sewerage project was cleared and tested yesterday, and is ready to be transferred to Addu City. Partial commissioning of the sewerage project is scheduled for September 2nd week.
Majority of project work is now complete, and outfall rectification process is currently ongoing. The revised value of the project is MVR 124.18 million. The project is estimated to be completed in January 2021.