The Harbour Repair and Dredging in R. Vandhoo is well underway

The Harbour Repair and Dredging in R. Vandhoo is well underway, with overall 35% project progress. The dredging of harbour basin work is now complete, and the installation of quay wall blocks is ongoing.
Additionally, project works include demolition of existing cement bag wall structures and depositing the debris. The estimated value of the project is MVR 5.99 million. The Ministry of National Planning, Housing and Infrastructure contracted the project to us on 26th August 2019.