11 Jun The HA. Hoarafushi airport development project is moving forward, with 83% project progress
The HA. Hoarafushi airport development project is moving forward, with 83% project progress. At the moment, delivery of asphalt and other materials needed for asphalt works are underway, and asphalt works are ready to begin.
Airport construction work involves construction of a 1200 m runway, 8,635m² of apron and taxiway, service roads at air and land side in front of terminal, 9,473m² of parking area, 1,718m² of fire access road and a 720m of airport security and beach fence area.
842,200 cubic meters of dredging and reclamation project work was completed in August 2019. A 1,120 meters of revetment was also completed in March 2020. Overall, our scope of the airport project will be completed by end Sept 2020.