The first shipment of quay wall blocks required for the Hdh. Neykurendhoo Harbor Development Project has been delivered to the project site

The first shipment of quay wall blocks required for the Hdh. Neykurendhoo Harbor Development Project has been delivered to the project site, and quay wall block installation work commenced on 13th July 2024.
Scope of works for this project include, new harbor dredging operations of 22,323cbm, maintenance dredging operations of 6,806cbm, channel dredging operations of 1,985cbm, construction of 366m breakwater, 166m revetment, 212m quay wall, 10m x 9m concrete ramp and installation of 1,859sqm harbor pavement, harbor and navigational lights, and mooring buoys. The value of the project is MVR 45.11 million.