15 Jul The first shipment of quay wall blocks required for the Hdh. Kurinbi Harbor Development Project have been delivered to the project site.
The first shipment of quay wall blocks required for the Hdh. Kurinbi Harbor Development Project have been delivered to the project site. Quay wall block installation work is currently ongoing at the site, and new harbor basin dredging operations have reached 51% completion.
Scope of works for the project include maintenance dredging operations of 7,071cbm, new harbor basin dredging operations of 32,381cbm, channel dredging operations of 2,040cbm, construction of 295m breakwater, 340m quay wall, 70m revetment, 10m x 9m concrete ramp, an access platform, and installation of 1,556.61sqm harbor pavement and harbor lights. The value of this project is MVR 42.45 million.