Settlement Tank installation work currently ongoing for Phase 2 of L. Fonadhoo Road Construction Project

Settlement tank installation work is currently ongoing under Phase 2 of the L. Fonadhoo Road Construction Project. Furthermore, we have completed 93% of stormwater pipe installation work and 53% of sidewalk construction work.

Scope of works include, construction of a 27,179 sqm carriageway, a 10,392 sqm pavement, installation of stormwater management system, road markings and streetlights. The value of the project is MVR 53.9 million.