Second shipment of rock boulders for the HA. Dhidhdhoo Harbor Extension & Jetty Construction Project has been delivered to the site.

The second shipment of rock boulders for the HA. Dhidhdhoo Harbor Extension & Jetty Construction Project has been delivered to the project site.

Scope of works include Dredging & Excavation operations of 78,000cbm, construction of a 378m breakwater, construction of 58m Groynes; 478m revetment; 630m quay wall, construction of 6,858sqm harbor pavement, a jetty, and supply and installation of navigation and harbor lights. The value of the project is MVR 70.59 million.