Road construction project of Hdh. Hanimaadhoo is well underway

Road construction project of Hdh. Hanimaadhoo is well underway, with overall 70% project progress. We have commenced ABC works on 4th April 2021 and we have scheduled to start asphalt laying works in May 2021.
Scope of works involve sidewalks of 16,518sqm; a carriageway of 38,916sqm, road markings of 19,679.7sqm. The project is valued at MVR. 46.7 million.