Velana International Airport South West Rectification work

Status

completed

About This Project

Velana International Airport South West Rectification Work was awarded to MTCC on 26th December 2017 by  the Maldives Airports Company Limited. The Project comprises of constructing quay wall with revetment & reclamation of existing road side, adjacent shores protected with revetment, commissioning and handover.

Scope pf the project included

  • Removal of Land side revetment head 470-meter
  •  Back fill and compaction of 470-meter
  • Laying of lean concrete pre-casting units on 470-meter
  • Casting of Pre-cast units 313nos
  • Placing of Removed rock boulders at a 470-meter area
  • Supply & placing of additional rocks on a 470-meter area
  • Placing of Filter Rocks at a 470-meter area
  • Extension of Geo fabric with 600gsm on a 470-meter area
Project Tpe
Shore Protection
Location
K. Hulhule'
Client
Maldives Airports Company Limited
Contract Sign Date
26th December 2017
Project Start Date
4th March 2018
Completion Date
28th June 2018