Harbour reconstruction project of V. Keyodhoo

Status

completed

About This Project

This project was awarded to MTCC on 13th July 2017 by the Ministry of Housing and Infrastructure. The project was completed on 15th May 2018.

 

This project included:

Dredging harbour basin 14,964 CBM

Sand cement bags Break water 68M

Construction of Quay wall 165 M

Beacon Installation 2 Nos

Harbour paving works 825 Sqm

Project Tpe
Harbour Construction
Location
V. Keyodhoo
Client
Ministry of Housing and Infrastructure
Contract Sign Date
13th July 2017
Project Start Date
5th October 2017
Completion Date
15th May 2018