Th. Madifushi Harbour Project was awarded to MTCC on 9th February back in 2014. The work for this project, awarded by the Ministry of Housing and Infrastructure, is currently on hold due to community-quaywall concept changing.
This project involves:
The dredging of harbour basin to -3M from mean water sea level
Construction of breakwater using rock boulder
Construction of precast concrete quay wall as per specification
Dredging works 20,210 M3
Breakwater 256 M
Revetment 20 M
Revetment from debris 98.24 M
Beacon installation 2 No’s
Quay wall 357 M
Harbour pavement 1010 M2.