Th. Guraidhoo Revetment

Status

completed

About This Project

This project was awarded to MTCC in 2015 by  the Ministry of Housing and Infrastructure.

 

The project scope included:

Construction of revetment on area -A 142m

Construction of revetment on area -B 93m

Construction of revetment on area -C 240m

Construction of revetment on area -D 321m

Construction of mega container & costal ridge on area -E 1154m

Construction of gorynes 80m

Project Tpe
Shore Protection
Location
Th. Guraidhoo
Client
Ministry of Housing and Infrastructure
Contract Sign Date
17th December 2015
Project Start Date
14th March 2018
Completion Date
14th February 2019