Harbour Breakwater Reconstruction Project of S. Maradhoo

Status

completed

About This Project

The construction of harbour at S. Maradhoo was signed between the Director General of Planning Ministry Fathimath Shana Farooq and the COO of MTCC Shahid Hussain Moosa, on 30th June 2019.

The project was mobilized on 03 November 2019.

Scope of works for the project included

  • Dredging operations of 18,873cbm
  • The construction of a 419m quay wall
  • A 340m revetment
  • A bridge measuring 40m length x 6m width
  • Installation of 1,975 sqm of paved area

We successfully completed MVR 28.2 million project on 29 November 2020.

 

Project Tpe
Harbour Construction
Location
S. Maradhoo
Client
Ministry of National Planning and Infrastructure
Contract Sign Date
30th June 2019
Project Start Date
3rd November 2019
Completion Date
29th November 2020