Repair Quay Wall of Male’ Commercial Harbour and South West Harbour

Status

completed

About This Project

The project to repair quay wall of Male’ Commercial Harbour and South West Harbour was awarded to MTCC in 2017 by  the Maldives Ports Limited.

 

The Project comprises of:

Dismantling of concrete panels of quaywalls and chipping of the damaged capping beam up to the existing reinforcement to allow new reinforcement bars to be welded to existing bars.

Eastern quaywall 92.68m

Western quaywall 1 – 73.00m

Western quaywall 2 – 79.00m

Western quaywall 3 – 103.00

Project Tpe
Harbour Construction
Location
Client
Maldives Ports Limited
Contract Sign Date
23rd December 2017
Project Start Date
1st March 2018
Completion Date
24th November 2018