R. Maduvvari Coastal Protection Project was awarded to MTCC on 4th September 2013. The work for this project, awarded by the Ministry of Environment and Energy, was completed on 7th June 2015. This project was to design and build a costal structure at R. Maduvvari.
The scope of the project included:
Dredging of sand 14,311.20 cbm
Delivery of rock boulders 15,200 ton
Delivery of 35 geotextiles
Construction of revetment 890m.