R. Innamaadhoo IDB Harbour Project – LOT2

Status

completed

About This Project

The construction of R. Innamaadhoo harbour was assigned to MTCC by Ministry of Housing and Infrastructure on 2nd December 2015. This project was concluded on 17th December 2017.

 

This project included:

Habour Demolition of existing Quay wall structures and depositing the debris to acceptable locations as directed by the Engineer 246 m

Demolition of existing breakwater structures and depositing the debris to acceptable locations as directed by the Engineer 151 m

Dredging Harbour basin to -3.00m level 20,077

Breakwater Construction:

Type 1 215 m

Quay wall construction:

Supply and fixing precast Quay wall units 304 m

Cast in situ concrete 304 m

Supply and fixing 38mm tie rod with 1000x1000x250mm anchor block 76 Nos

Supply and fixing 38mm tie rod with 500x750x250mm anchor block 75 nos

Supply and fixing 20mm SS hooks 56 Nos

Back filling behind quay wall 2,324 cbm

Others:

Mooring buoys 13 Nos

Fixing solar powered Navigation lights 2 Nos

Construction of Fish landing slab 48 sqm

Project Tpe
Harbour Construction
Location
R. Innamaadhoo
Client
Ministry of Housing and Infrastructure
Contract Sign Date
2nd December 2015
Project Start Date
29th April 2016
Completion Date
17th December 2017