The R. Inguraidhoo construction of harbour project was awarded to MTCC in 2015 by the Ministry of Housing and Infrastructure. The project was completed during 2019.
The project included:
Dredging/excavation of any material for the new harbour basin, maximum specified depth -3m MSL 2168cbm
Armour rocks laid to the slopes defined in drawings and to lines and levels indicated in the cross section drawings. Rate shall include levelling and placing armour rocks 288m