H.A. Dhihdhoo Design and Build of Coastal Protection Structures

Status

completed

About This Project

The project to design and build coastal protection structure at H.A. Dhihdhoo was assigned to MTCC by the Ministry of Environment and Energy.

 

Main components of this project included:

Dredging 11300.00 cbm

Rock boulder revetment 450.00 m

Concrete staircase 2 no’s

Project Tpe
Shore Protection
Location
H.A. Dhihdhoo
Client
Ministry of Environment
Contract Sign Date
12th May 2016
Project Start Date
15th October 2016
Completion Date
20th April 2017