M. Mulah Breakwater Construction

Status

completed

About This Project

M. Mulah breakwater construction was awarded to MTCC on 12th May 2011 by the Ministry of Housing and Environment. The work for this project, valued at MVR 15,445,784.012, was completed on 28th March 2013.

Project Tpe
Harbour Construction
Location
M. Mulah
Client
Ministry of Housing and Environment
Contract Sign Date
24th May 2011
Project Start Date
25th July 2012
Completion Date
28th March 2013