L. Gan Mukurimagu Harbour Infrastructure

Status

completed

About This Project

L. Gan Mukurimagu harbour infrastructure was awarded to MTCC on 8th July 2008 by Ministry of Construction and Public Infrastructure. The work for this project, valued at MVR 29,735,044.47 was completed on 28th August 2010.

Project Tpe
Harbour Construction
Location
L. Gan
Client
Ministry of Construction and Public Infrastructure
Contract Sign Date
8th July 2008
Project Start Date
25th July 2008
Completion Date
28th August 2010