K. Maafushi Design and Build of Coastal Protection Structures

Status

completed

About This Project

Awarded in 2015, K. Maafushi coastal protection project was signed between MTCC and the Ministry of Environment and Energy. The construction of the 280 meters of rock boulder revetment commenced on the 10th of February 2016. Work on this project was completed on 29th August 2016. The project was funded by the Government of the Maldives and was awarded to MTCC for MVR 14 Million.

Project Tpe
Shore Protection
Location
K. Maafushi
Client
Ministry of Environment and Energy
Contract Sign Date
27th October 2015
Project Start Date
10th February 2016
Completion Date
29th August 2016