Excavation and Back filling work at H.Dh. Kulhudhuffushi Airport Terminal

H.Dh. Kulhudhuffushi Terminal Excavation and Back Filling project was awarded to MTCC in 2018 by the Regional Airports. This project was completed on 25th September 2018

Scope of the project included

  • Terminal area Excavation 7,125-square-meters
  • Disposal of unsuitable materials 4,500.00-cubic-meters
  • Terminal area backfilling 8,250.00-cubic-meters
  • General leveling – Terminal area 3,750.00-square-meters

The project cost is MVR 1305811.35.

Status
completed
Category
Sewage Works
Project Type
Airport Construction
Location
H.Dh. Kulhudhuffushi
Client
Regional Airports
Contract Sign Date
19th September 2018
Project Start Date
15th September 2019
Completion Date
25th September 2018