Excavation and Back filling work at H.Dh. Kulhudhuffushi Airport Terminal
H.Dh. Kulhudhuffushi Terminal Excavation and Back Filling project was awarded to MTCC in 2018 by the Regional Airports. This project was completed on 25th September 2018
Scope of the project included
- Terminal area Excavation 7,125-square-meters
- Disposal of unsuitable materials 4,500.00-cubic-meters
- Terminal area backfilling 8,250.00-cubic-meters
- General leveling – Terminal area 3,750.00-square-meters
The project cost is MVR 1305811.35.