H.Dh. Kulhudhuffushi Terminal Excavation and Back filling work

Status

completed

About This Project

H.Dh. Kulhudufushi terminal excavation and back filling work was handed over to MTCC by Regional Airports.

The project was completed in 2018.

Scope of this project included

– Excavation of 7,125-square-meter at the terminal area
– Disposal of unsuitable materials of 4,500-cubic-meter
– Backfilling works on an area of 8,250-cubic-meter for the terminal area
– General leveling of 3,750-square-meter at the terminal area